Posted: July 26, 2018
Last modified: July 30, 2018

UPDATE: Due to heavy rains the night of Friday, July 27, the opening of the new traffic pattern at the Wymore Road-Douglas Avenue and State Road (S.R.) 436 intersection has been delayed. Barring any additional weather delays, I-4 Ultimate crews are now scheduled to open the new traffic pattern on the morning of Sunday, July 29.

The permanent change at the intersection means traffic will no longer be able to cross S.R. 436 between Wymore Road and Douglas Avenue. Wymore Road and Douglas Avenue will become right-in, right-out only from S.R. 436. Pedestrians and right-in and right-out traffic will still be guided by the existing traffic signal. Once the S.R. 436 interchange is completed and the pedestrian tunnel opened, the traffic signal at S.R. 436 and Wymore Road/Douglas Avenue will be removed to provide more capacity for vehicles accessing I-4 and to improve traffic flow.

Lanes on Westmonte Drive also will be added or widened to accommodate the additional volume of motorists using the roadway. Construction on these roadways began in 2017 in anticipation of motorists using this new traffic movement. The signals throughout these roadways will be adjusted and timed to accommodate the additional capacity.

To view or download a handout detailing the new traffic pattern, please visit www.i4ultimate.com/douglaswymore.

Modifications or extensions to this schedule may become necessary due to weather delays or other unforeseen conditions. Motorists are advised to maintain a safe speed when driving through the work zone.